What is the name for the chain of tasks whose duration determines the project duration?

What is the name for the chain of tasks whose duration determines the project duration?

Answer

the critical path

Its defining property is zero slack — a day lost on any task in the chain is a day lost on the delivery date.

Pressman 9e ch25 §25.7–25.10