~/ learn/ comp-410/ cards/ Configuration Management, Metrics, and Support
1 of 33

Complete the IEEE definition: a baseline is formally reviewed and agreed, thereafter serves as the basis for further development, and can be changed only through ___.

Complete the IEEE definition: a baseline is formally reviewed and agreed, thereafter serves as the basis for further development, and can be changed only through ___.

Answer

formal change control procedures

The third clause is the one candidates drop, and it is the clause that distinguishes a baseline from any other saved version.

Pressman 9e ch22 §22.1–22.4

space flip · ← → navigate · esc to exit
NORMAL ~/memra/library/69af1147-5592-4ed6-8057-994196813f80/flashcard utf-8 LF